This contract includes the following elements:
_ installation of transit and distribution pipelines of diameter DN32 to DN400, with approximate length of 92 km,
_ construction of new reservoirs and installation of flow meters.
_ reconstruction of the existing water supply network,
_ reconstruction of the transit pipeline from BC Lašor to the reservoir Zagrablje,
_ construction of the new reservoir Sandin vrh 1 and booster station Sandin vrh 2,
_ reconstruction of the pumping station Višnjica and the breaking chamber Velja Gora
Works will be implemented according to FIDIC Red Book (1999 ed).
Works shall be implemented in compliance with the requirements of the Montenegrin legislation and relevant EU and EIB requirements. The Contractor must particularly consider licensing and permits requirements in the Law on Construction of Structures in Montenegro in force.
45200000: Komplett- oder Teilbauleistungen im Hochbau sowie Tiefbauarbeiten